Manitowoc Cranes Build Wind Turbine in Four Days
![]() |
Enlarge Image. |
December 7,
2011–Two Manitowoc cranes
installed a wind tower in Cleveland, Ohio, over a four-day period earlier this
year. Located outside the headquarters of Lincoln Electric, the 443-foot turbine
is one of the largest urban wind towers in North America.
A
Manitowoc 16000 crawler crane and a Grove GMK5120B all-terrain crane from All
Erection & Crane Rental Corp. were utilized to erect the 2.5 MW turbine.
The first task
of the project was off-loading and erecting the four tower sections from their
delivery trucks. The sections were lifted and walked into position by the Model
16000, with the GMK5120B providing tailing support. Each section weighed
approximately 70 tons.
With the tower
sections installed, the cranes then worked together to install the 99-ton
nacelle and drive train, which was handled in two lifts. Finally, three rotor
blades were bolted together at ground level before the entire 64-ton assembly
was carefully lifted into place.
Following completion
of the $5.9 million project, Lincoln Electric staged an inauguration ceremony to
celebrate its success. “The cranes on this job performed admirably and
everything ran smoothly and on time,†said George Blankenship, president of
Lincoln Electric North America.
A third crane, a
30-ton RT530E-2 from Grove’s rough-terrain range, was also used in the early
stages of construction for land preparation.
All Erection &
Crane Rental Corp. rigged the 440-ton capacity Manitowoc
16000 crawler crane with 157 feet of main boom and 177 feet of luffing jib for
the project. The crane can accommodate a maximum of 432 feet of main boom. All
Erection sent the crane to site on 22 trucks.
The Grove GMK5120B is
a 120-ton capacity all-terrain crane with a 167-foot boom mounted on a five-axle
carrier.
